The Missouri Department of Transportation has announced that bridge painting projects have been scheduled to begin in May (weather permitting.) The seven bridges that are scheduled to be painted were constructed last year under the Safe & Sound Bridge Improvement program. The following is a list of bridges that will be painted in the upcoming weeks:
Caldwell County:
MO 116 - North Mud Creek
Route N - Mud Creek
Dekalb County:
MO 33 - (two bridges south of Maysville) West Fork Lost Creek & Branch of Lost Creek
Harrison County:
Route MM (two bridges) - Fox Creek & Sugar Creek
Route AA - Big Creek
Each bridge will take up to two weeks to paint. During different stages of this process the bridges will be narrowed briefly to one lane and flaggers will be directing traffic across the bridges. The work on the bridges listed above will be staged and work will begin in Caldwell County on MO 116.
For more information about this or other projects being handled by MoDOT please call our toll-free customer service hotline at: 1-888-ASK-MoDOT (1-888-275-6636).