Friday, July 7, 2023

Weekly Area Road Work for July 9th to 15th, 2023

Gentry County

Route YY – CLOSED until further notice at the Bear Creek Bridge due to deterioration. This bridge is included in a replacement project scheduled to be a part of the September 2023 letting for contractor bids. https://www.modot.org/atchison-and-gentry-counties-bridge-replacements

U.S. Route 136 – Resurfacing project from U.S. Route 169 to Route J (Nodaway County) through mid-August. A 12-foot width restriction is in place. (Contractor: Herzog Contracting Corp.)

Route E – CLOSED for a bridge replacement project at the Walnut Fork Bridge through August. (Contractor: North Central Bridge, LLC.) More info: https://www.modot.org/gentry-county-route-e-walnut-fork-bridge-replacement-project

Route T – CLOSED for a bridge replacement project at the Brushy Creek Bridge through October. (Contractor: Lehman Construction and Wilson & Company) *2

Route T – CLOSED for a bridge replacement project at the Fitzgerald Creek Bridge through mid-November. (Contractor: Lehman Construction and Wilson & Company)*2

Harrison County

Route D – CLOSED for a bridge replacement project the Ames Creek Bridge, west of Bethany, through early October. (Contractor: Lehman Construction and Wilson & Company) *2

I-35 – Concrete replacement from mile marker 81 to mile marker 84, July 11. The road will be narrowed to one lane at various locations in both directions around-the-clock.

Nodaway County

U.S. Route 136 – Resurfacing project from Route J to U.S. Route 169 (Gentry County) through mid-August. A 12-foot width restriction is in place. (Contractor: Herzog Contracting Corp.)

Route 46 – Pavement and guardrail improvements project from Country Club Road to Katydid Road, through July. A 12-foot width restriction is in place. (Contractor: Herzog Contracting Corp.)

Route N – CLOSED for a culvert replacement from 390th Street to 400th Street, July 13, 6:30 a.m. to 3 p.m.

Worth County

Route A – CLOSED for a bridge replacement project at the Branch Bridge through early November. (Contractor: Lehman Construction and Wilson & Company) *2

Legend

*1 This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state.

*2 This bridge is part of the FARM (Fixing Access to Rural Missouri) Bridge Program. More info: FARM Bridge program web page

*3 This bridge is a part the Safe & Sound bridge rehabilitation project. More info: https://www.modot.org/safe-sound-bridge-rehabilitations-buchanan-carroll-gentry-harrison-counties

*4 This project is part of Gov. Parson’s Rural Road program. The state’s approved Fiscal Year 2023 budget provided an additional $100 million in General Revenue for work on Missouri’s low volume rural roads. Using asset management data, MoDOT has identified approximately 1,700 lane miles of low volume roads ranked in Poor Condition. By next summer, these 113 locations will receive resurfacing treatments of hot mix asphalt to improve the road conditions.


No comments: