At the Nodaway County Commission meeting Thursday, Nina Wiederholt asked if the county could require local purchases when possible since data centers in Missouri are taking advantage of a sales tax loophole that was implemented by the state in 2015.
Under Missouri law, Missouri's Data Center Sales Tax Exemption program allows qualifying data centers to receive exemptions on sales and use taxes related to construction, equipment, computers, machinery, and utilities. To qualify, a new data center must invest at least $25 million in new investment and 10 new jobs meeting specified wage requirements. Expanding facilities have lower thresholds. The White Cloud Acres project website touts 1,000+ construction jobs, 130+ long-term jobs, and $1.1 billion in local investment over the life of the project.
More about the eligibility for the project for state incentives will be known when the end user is known. The end user for the proposed data center is not known.
The exemption is limited for up to 15 years for qualifying new facilities and up to 10 years for expansions. It only applies to eligible purchases.
Missouri also allows Chapter 100 bonds; however, that is up to the Nodaway County Commission, and they have taken no action on such a move.
"You'd be surprised how much work some of our current manufacturers have from data centers," said Nodaway County Economic Developer Josh McKim.
Mr. McKim said that on the Evergy substation project, which is separate from the proposed data center project, the contractor has made a concerted effort to use local businesses and hire local people.
Donna Tompkins said that she recently nearly wound up in the ditch because she couldn't see where the road is on Route 71 when one is trying to get from it to 340th Road or vice versa near the Evergy project.
Commissioner Chris Burns said that if they were to purchase items from out of the area, it would fall under use tax. For instance, the county collected use tax when the wind farm was built.
Susie Strauch said that the surveyors were back. It was the third group of surveyors that has been at the proposed site. The first were surveyors from Scale Microgrids, and the second was a contractor. These were contractors out of St. Louis. They were taking soil samples, and Grand River Mutual has been marking lines where the proposed gas turbines would go.
Commissioner Burns said that a committee consisting of six people is getting the commissioners information about zoning and data centers. The committee is advisory and does not have zoning power. Members are Tim Lance, Mike Rosenbohm, Eric Houts, Bill Engels, Brooke Kinsella, and Jared Stiens.